15-Storied Head Office DPE

15-Storied Head Office DPE

Planning, designing, survey, Inventory, Architectural design, Structural design, Plumbing & Sanitation design, Electrical & Electro-Mechanical design, Preparation of estimate, Specification, Tender Document and Construction management, Construction supervision, Quality control, testing of materials, Payment certificate, Liaison with the authority, progress report etc. Over all responsibility of successful implementation of the project. Construction Supervision 1st- Phase. 15- Storied Foundation + 2- Basement, Pile Foundation, MAT Service Pile, Short- Pile etc.Planning, Designing & managing Construction of 15- storied Office Building with 2- Floor basement for Parking, Air- conditioning System, Lift-4 nos. Fire Fighting, Aluminum curtain wall etc.